Bryanston School Property Tennis & Pickleball Courts - Repairs

Date

The tennis and pickleball courts at the Bryanston School Property will be closed for two to three weeks in April and May to allow for court repairs and repainting. Work will start April 15, 2024.

Project Scope

Scope of work taking place:

  • Grinding of existing asphalt to remove cracking
  • Fill grinded areas with new asphalt
  • Add finish layer of asphalt over entire court area
  • Paint tennis and pickle ball markings

Project Updates

April 25, 2024 - Middlesex Paving and Maintenance completed the asphalt project at the Bryanston School Property. In a few weeks, after the asphalt has cured, we will look to repaint all lines.

Bryanston Courts in Progress 2024

Alternative Courts

Please visit an alternative court during the closure periods:

Questions

For questions about this project please contact Justin Fidler, Operations Manager, Community Services, Middlesex Centre.

 

This page was first posted April 15, 2024.