Vanneck Road Reconstruction

Date
Image
Road Closed Ahead Sign

Middlesex Centre will be reconstructing Vanneck Road between Egremont Drive (CR22) and Medway Road this summer.

Project Details

Location:

  • Vanneck Road Reconstruction between Egremont Drive and Medway Road
  • Once 

Schedule:

  • Start date – June 1, 2026
  • Estimated completion – August 14, 2026

Scope:

  • Reconstruction of the roadway, ditching, culvert replacements, select tree trimming and removals, and asphalt resurfacing

Contractor:

  • Municipality of Middlesex Centre and asphalt contractor

How will Construction Impact You?

If you live or travel along the streets being resurfaced, please note:

  • Street Access and Parking: Localized road closures are expected during construction only allowing local traffic to access their properties. A detour route will be in effect during construction with the appropriate signage to direct traffic. Additionally, information on detours and closures will be posted to Municipal 511 once construction begins.
  • Vibration & Dust - Protect Valuables: Construction equipment can cause vibrations and dust. Please ensure you protect any valuables susceptible to damage. Staff will monitor dust conditions and apply dust suppressants as required to minimize dust due to construction.
  • Mail Services: Canada Post will continue to deliver mail during construction. Canada Post will provide further notification and instructions for residents that may be impacted. Staff will provide temporary mailboxes that are temporarily removed or impacted due to construction.
  • Waste and Recycling Collection: If your pick-up point is temporarily blocked by construction, the Municipality will assist in collecting and transporting your garbage and recycling.
  • Manicured Lawns: The municipality will restore all damaged manicured lawns resulting from the construction project. A mixture of seed and water will be applied by the municipality to such affected locations. We encourage you to assist in the watering process.
  • Sprinklers, Flower Beds, Invisible Fences, and Private Infrastructure: Residents are encouraged to remove any private infrastructure and items that may be inadvertently located in the municipal boulevard. The municipality will not be responsible for or repair any private infrastructure damaged or removed as a result of this work. 

Questions?

If you have questions or concerns about this project, please contact Andrew Giesen, Transportation Manager.

If there is a construction related emergency and there are no staff on-site to report it to, please contact the municipal office or use the Report a Concern webform.

 